A southwest Iowa RV and trailer service shop called us in the middle of a February cold snap asking whether a 2 post car lift could realistically live in a building that already had a 14-foot overhead door, a swinging man-door on the north wall, and a mezzanine over the parts counter. They were tired of turning away alignment work on tow vehicles and light-duty trucks because everything they owned rolled on jack stands. We measured, we argued about a few inches, we ordered, and we installed. What follows is the honest version of that first year of ownership — the clearance math, the door-swing problem nobody thinks about until the arms are on, and what the equipment actually did for their alignment bay once it was in service.
Rotary, Challenger, BendPak and Atlas two-post models in 9,000 through 18,000 lb capacities. Not sure what fits your ceiling or your concrete? Call us at 800-674-9302 and we will run the numbers with you before you spend a dime.
Why an RV and Trailer Shop Wanted Two Posts Instead of Four
Most people assume an RV shop needs a four-post or a set of mobile columns, and for the big Class A coaches that is true. But this business made the bulk of its money on tow vehicles, cargo trailers, and the half-ton and three-quarter-ton trucks that pull them. Those are the vehicles that come in with a pull to the right after 40,000 miles of gooseneck duty. A four-post is wonderful for storage and quick service, but it puts a runway under the tires, and the runway is exactly where you do not want steel when you need wheels-free access to tie rods, ball joints, and control arm bushings.
A two-post hangs the vehicle by the frame and leaves the entire underside open. For alignment work specifically, that matters less than it does for suspension repair — a true alignment rack is usually a four-post with slip plates and turnplates — but this shop’s realistic volume did not justify a dedicated rack. They wanted to pull a worn tie rod end, replace a bad hub, set toe on a portable head system, and get the truck out the door. The open-center design of a two-post made every one of those jobs faster. They also wanted the bay to stay usable for brake work, exhaust, and driveline service on the same footprint, which the runway design would have complicated.
Ceiling Height Is Not One Number, It Is Three
Everybody calls and tells us their ceiling height. Almost nobody tells us the right number. When we walked the southwest Iowa building, the peak of the ceiling was just over 15 feet, but the bottom of the steel purlin over the intended bay was 13 feet 4 inches, and a sprinkler main crossed at 12 feet 9 inches about six feet off the proposed column line. That third number was the one that mattered. An overhead-style two-post typically needs somewhere in the 12 to 14 foot range depending on the model, and the overhead beam has to clear everything, not just the highest point in the room.
We ended up moving the bay about four feet south to get out from under the sprinkler main, which cost them a little bit of parts-counter walking distance but saved a plumbing relocation that would have run into real money. If the main had not been movable and the purlin had been lower, the answer would have been a baseplate model — a floorplate design that runs the equalization cables through a low channel across the floor instead of an overhead beam. Baseplate lifts open up buildings with 10 to 11 foot ceilings, and we sell plenty of them for exactly that reason. The tradeoff is the floor channel, which you will drag a creeper over and occasionally trip on. In an RV and trailer shop with rolling jacks and tire carts moving constantly, the overhead was the better call once we found the clearance.
The Door Swing Problem Nobody Plans For
Here is the detail that caught this shop off guard, and it catches almost everyone: the arms on a 2 post car lift swing through a huge arc, and that arc does not care about your walls, your air hose reel, or your man-door. Fully extended and swung out to the side, an asymmetric arm on a 10,000 lb unit can reach five feet or more past the column. The shop had planned the column spacing beautifully and then discovered on install day that the driver-side rear arm, at full extension and swung rearward, contacted the north man-door when that door was open.
We solved it by rehanging the door to swing the other direction, which took an hour and a $30 hinge set. But if that door had been an exterior fire exit with code requirements about swing direction, we would have been shifting the entire column line instead. This is why we ask for a sketch with wall locations, door locations, door swing arrows, and overhead obstructions before we quote an install. It costs you ten minutes with a tape measure and saves everybody an ugly conversation on install day. The same logic applies to compressor lines, floor drains, and electrical panels — a two-post needs roughly three feet of walking room on the outside of each column, and it needs the arms to swing clean through their entire range without hitting anything solid.
Concrete, Anchors, and the Six-Inch Question
Concrete kills more two-post installs than ceiling height does. The general standard for a 10,000 lb model is four inches minimum of 3,000 PSI concrete, though most manufacturers want more, and we would rather see six inches under a shop that lifts trucks all day. This building had a slab poured in the late 1990s. We core-drilled two test holes and found a consistent five and a half inches of decent concrete with no rebar in the way — good enough, and honestly better than most rural Iowa shop floors we test.
What you do not want is to guess. We have been called to shops where the floor looked identical across the whole bay and turned out to be four inches on one side and two and a half over a filled-in pit on the other. Anchors pulling out of thin concrete under load is the single worst failure mode on a two-post, and it is entirely preventable with a core sample or a hammer-drill test hole. If the concrete comes up short, the fix is a cut-out and a new pad — typically a 10 by 12 foot section poured to six or eight inches with proper cure time before you set the columns. That is a real expense, but it is a fraction of what a dropped truck costs. We would rather tell you no in the estimate phase than install a 2 post car lift onto a slab that cannot hold it. If you are unsure what your floor looks like, our piece on concrete requirements for car lifts walks through the testing process step by step.
Install Week: What Actually Happened
The install itself took a day and a half. Day one was layout, core testing, drilling anchors, and setting both columns plumb. Anybody who has set a two-post knows the columns have to be square to each other and plumb within a very tight tolerance, and shimming is normal — almost no shop floor is flat enough to skip it. We used a laser level and shimmed the passenger column about three-sixteenths of an inch at the base. Day two was the overhead beam, the equalization cables, the hydraulic lines, the power unit, and the electrical.
Electrical is where a lot of DIY installs stall out. Most single-phase power units on this class of equipment want a dedicated 220V circuit at 30 amps. This shop had 220 in the building but no drop near the new bay, so their electrician ran a new circuit while we finished the mechanical side. That is a coordination item worth handling two weeks before install, not the morning of. Once the unit was wired, we cycled it empty a dozen times, bled the cylinders, set the safety lock engagement, adjusted the arm restraints, and ran a full-load test with the shop’s own three-quarter-ton truck. The shop foreman put a level on the crossbar, watched all four safeties click in sequence, and that was that. First real job on the equipment was a set of upper control arms on a Super Duty that afternoon.
Twelve Months In: Maintenance, Wear, and Surprises
We went back at six months and again just past the one-year mark. The honest report: nothing dramatic broke. What did happen was ordinary and predictable. The equalization cables stretched slightly in the first two months, as they always do, and needed a re-tension so both carriages arrived at the top together. Anybody who has watched a two-post go up unevenly knows that sound — it is not a failure, it is a cable adjustment, and it should be checked at 30 days, 90 days, and annually thereafter.
The arm restraint pins on the driver’s side wore faster than the passenger side, which made sense once we watched them work — the tech loading trucks always approached from the same angle and dropped the driver arms harder. We swapped both pin assemblies at eleven months. The lift pads took a beating from truck pinch welds and got replaced once. Fluid level in the power unit dropped a half inch over the year with no visible leak, which is normal seepage past seals and cured by topping off with the correct hydraulic oil, not automatic transmission fluid, no matter what somebody at the counter told you. The shop now runs a written monthly checklist: check cables, check anchors for looseness, check fluid, look at hoses, cycle safeties. That checklist is the entire difference between a 2 post car lift that lasts twenty years and one that gets replaced in eight. Our guide on two-post lift maintenance schedules covers what we recommend for a commercial-duty shop.
Choosing Capacity, Symmetric vs. Asymmetric, and What We Would Buy Again
This shop bought a 10,000 lb clear-floor overhead model, and after a year they told us they should have gone to 12,000. That is the most common regret we hear. The heaviest thing they lift is a loaded three-quarter-ton at maybe 8,200 pounds, so 10,000 is technically fine. But dually conversions, service beds, and the occasional customer who leaves 800 pounds of tools in the bed eat that margin fast. Stepping up one capacity class costs less than most people assume and buys you a decade of not thinking about it.
On symmetric versus asymmetric: symmetric puts the vehicle centered between the columns with equal-length arms and works well for trucks and vans where you want maximum stability and do not care much about door opening. Asymmetric rotates the columns and uses shorter front arms so the vehicle sits back, letting car doors open past the column. An RV and trailer shop working mostly trucks leans symmetric. A general repair shop that sees a lot of sedans leans asymmetric. Plenty of modern designs split the difference and let you set the arms either way. For brands, we install and stock parts for Rotary and Challenger on the commercial side and BendPak and Atlas for lighter-duty and home use, and we will tell you straight which one fits your budget and your building. If you want help sizing a 2 post car lift for your own bay, or you already own one and it stopped going up, call 800-674-9302 and we will work through it. You can also read our comparison of symmetric vs. asymmetric two-post lifts before you commit.

Our Clients Include: