Before you get auto lifts installed in a new farm shop outside West Des Moines, the sequencing of your build-out matters more than most people expect. We got a call not long ago from a guy setting up a shop between planting seasons who’d already poured his slab and framed his walls before he thought about where his lift columns needed to sit, or how much clearance he’d need overhead to pull a bearing hub on a one-ton dually. He wasn’t wrong to want the lift — he just had the order backward. If you’re staring down a bare pole barn or a half-finished shop and you’re serious about doing your own wheel bearing service, this is the checklist we walk customers through before a single bolt goes into concrete.

Shop 2-Post Lifts →

Browse the lifts we install across Iowa, from home-garage 2-post units to heavy-duty farm shop setups built for wheel bearing and axle work.

Why Sequencing Comes Before Auto Lifts Installed on the Slab

Most farm shop owners think about the lift last, after the walls are up and the slab is cured. That’s backward. The single biggest mistake we see is a slab poured to a generic thickness without any thought to where the columns or anchor bolts will land, or how thick the concrete needs to be under a 10,000-lb or 12,000-lb two-post unit. Wheel bearing service on farm trucks and equipment trailers puts real lateral load on a lift, and if the pad under your columns isn’t rated for it, you’re looking at a redo before you’ve even made your first bearing swap.

We’ve had customers who paid a full invoice on good faith for a lift install, only to find out months later the concrete wasn’t right and the whole thing had to be repoured and reinstalled. That’s an expensive lesson to learn after the fact. Before you finalize your building plans, call whoever is going to get your auto lifts installed and ask them to review your slab spec, not just your floor plan. A five-minute conversation up front about pad thickness, rebar, and column spacing saves you a five-figure headache later. This is the first line item on any real pre-purchase checklist, and it’s the one people skip most often because it feels like a detail for later.

Ceiling Height and Overhead Clearance for Wheel Bearing Work

Wheel bearing service means you need real working height above the vehicle, not just enough to drive it in. If you’re running a two-post lift and pulling hubs on a 3/4-ton or 1-ton truck, you want clearance to swing a breaker bar, work an impact gun overhead, and still have room for the tire off to the side. We ask every farm shop customer what the tallest vehicle or trailer axle they’ll service is, then we back into the ceiling height and lift arm reach from there.

This is also where four-post drive-on lifts sometimes make more sense than people assume for wheel bearing work, especially if you’re servicing gooseneck trailers or dual-wheel trucks where a two-post’s arm placement gets tight. We’ve installed both configurations in rural Iowa shops, and the right call usually comes down to your actual vehicle mix, not what looks impressive in a catalog. Get this measured against your actual roof trusses and any door header height before you order equipment, not after it shows up on a truck.

Power, Air, and What Actually Needs to Be in the Wall

A lift install isn’t just the lift. Rolling jacks and air kits are often bundled into the installation, and both need dedicated air lines and, depending on the lift, a proper electrical circuit run before drywall or steel panels go up. We’ve handled jobs where the shop owner assumed a standard 110V outlet would cover it and had to have an electrician back out for a rewire after the walls were already closed in.

If you’re building out a shop specifically to get auto lifts installed for bearing and brake work, put your air compressor location, air drop points, and lift power run on the plans before the walls close. This also affects where your lift can physically sit — you don’t want your air lines fighting your column placement. Talk to your installer about whether you need a 220V single-phase or three-phase run, because that decision changes what’s in your walls, and it’s far cheaper to run conduit now than to fish wire through finished steel later.

Forklift, Freight, and Getting the Lift On Site

Rural shops near West Des Moines often don’t have a loading dock or a warehouse crew standing by, so freight logistics matter more than people expect. A two-post or four-post lift ships heavy, usually on a flatbed, and someone needs a forklift or equivalent equipment to get it off the truck and staged near the install site. We ask every customer this directly before scheduling: do you have a forklift on site, or do we need to bring one?

We’ve scheduled installs around exactly this question more than once — a shop with the lift already delivered and a forklift ready to go moves a lot faster than one where we’re improvising with a tractor bucket. If your shop is remote, factor in lead time for freight delivery too, since rural delivery windows can run longer than in-town scheduling. Confirm your driveway and shop door clearance can handle a flatbed delivery, because a farm lane that’s fine for a grain truck isn’t always wide enough for a freight rig with a lift crated on it.

Pit or No Pit: A Decision That Changes Everything Else

Some farm shop owners ask about in-ground lifts because they’ve seen them at a dealership, but for wheel bearing work in a rural setting, an above-ground two-post or four-post almost always makes more practical sense. In-ground installs require a pit, which means extra excavation, drainage planning, and a level of concrete work that most pole-barn shops aren’t built for. Unless you’ve got a specific reason to go in-ground, we steer farm shop customers toward surface-mounted lifts because they’re faster to install, easier to relocate if you ever change the shop layout, and don’t require re-engineering your slab drainage.

That said, if you know you want a pit-style lift down the road, that’s a decision that has to be made before the slab is poured, not after. Retrofitting a pit into an existing shop floor is a much bigger job than building it in from the start. Talk through your long-term plans with whoever is quoting your auto lifts installed, even if a pit isn’t part of this phase of the build.

Payment Terms, Warranty, and Protecting Yourself as the Buyer

We’ve heard from more than one shop owner who got burned by a botched install elsewhere — paid in full up front, then discovered problems only after the crew was long gone, and ended up eating the cost of a concrete repour and reinstall themselves. That’s exactly the kind of situation a good pre-purchase checklist should protect you against. Ask any installer directly about their payment structure, whether a deposit is standard, and what happens if something needs correction after the fact.

We don’t require a large upfront deposit before we’ve even seen your site, and we stand behind our own work rather than treating an install as done the moment the invoice is paid. Before you sign anything, get the installer’s terms in writing, ask what their process looks like if a redo is needed, and don’t be afraid to ask pointed questions about accountability. A legitimate installer will have straightforward answers, not vague reassurances.

Matching the Lift to Real Farm Shop Work

Wheel bearing service on farm trucks, trailers, and the occasional piece of equipment is different from a typical dealership bay, and your lift choice should reflect that. Weight capacity matters more here than in a passenger-car shop — a loaded dually or a trailer axle can push toward the upper end of a standard lift’s rating, so we always ask about the heaviest unit you’ll realistically service before recommending capacity. Undersizing a lift to save money up front is one of the more common regrets we hear about a year or two into ownership.

We generally point farm shop customers toward two-post lifts in the 10,000 to 12,000-lb range for this kind of work, sometimes stepping up if heavier equipment is in the mix. Once you’ve settled on capacity, the rest of the checklist — slab, clearance, power, freight, and payment terms — falls into place around that choice. Getting auto lifts installed correctly the first time, in a shop actually built around how you’ll use it, is worth the extra planning before you ever pour concrete.

About the Author

Josiah Ragsdale is the founder of Auto Lift Services. Based in Ames, Iowa, our team installs, services, and stocks parts for every major lift brand — from a home-garage 4-post through 30,000 lb commercial and 40K+ heavy-duty. Have a question or need a quote? Call 800-674-9302 or email [email protected].