A weekend hobbyist mechanic in Ankeny was building a new detached shop behind his house and called us before the concrete was poured to ask about auto storage lifts. He wanted to store his summer car under his daily driver during winter, run tire rotations and wheel work himself, and have room for one project truck long-term. His question was smart: what order should he sequence the build-out so the lift decisions did not force expensive changes later? That is the right question and almost nobody asks it before the slab is poured. Here is the sequence we walked him through, in the order you should think about it.
Free planning call. We spec the lift before you spec the concrete.
Step 1: Pick the lift before you pour the slab
This is the single most important sequencing decision. Auto storage lifts anchor into concrete with wedge anchors that need a minimum of 4 inches of good concrete at 3,000 PSI or better. Most residential garages pour 4 inches, which is the minimum. If you know a lift is coming and you have not poured yet, pour 6 inches with number 4 rebar on 12-inch centers in the lift zone. It costs a few hundred dollars extra on the concrete pour and eliminates the anchor-torque risk entirely. He was in the perfect position to make this call because his concrete contractor had not started yet. We faxed the anchor pattern drawing to the contractor the same afternoon.
Step 2: Frame the walls for the ceiling you need
Standard residential detached garages frame with 8-foot or 9-foot walls. Neither one clears a stacked pair of auto storage lifts with a full-size vehicle on top. You need at least 11 feet 6 inches from finished slab to lowest overhead obstruction. That usually means 12-foot walls and a scissor truss to keep the ceiling flat and clear. He upgraded to 12-foot walls in the design phase, which added about the cost of a decent stereo system to the total build. That upgrade was cheaper by an order of magnitude than tearing off a roof later to fit a lift.
Step 3: Size the garage door for a truck on the lift
A garage door has to clear the tallest vehicle you plan to drive through it. If you plan to drive a truck out of the garage while another vehicle is stored above on a lift, the door has to clear the truck. That is normally not a problem because the door opening is separate from the ceiling. What people miss is the header above the door. In a 12-foot wall, the door header often drops the effective opening to 10 feet or less, and that can rule out full-size dually trucks. We told him to spec a 10-foot-tall door with a low-profile track, which kept the door opening functional in a 12-foot wall.
Step 4: Wire the electrical for the lifts before you drywall
Auto storage lifts need dedicated 220-volt 30-amp circuits from the panel to the lift location. Running the wire before drywall goes up is trivial. Fishing wire after the fact is expensive and always looks bad. We recommended one circuit per lift position and one extra circuit for a future third lift. Total electrical cost for the three circuits, at the framing stage, was less than the cost of a set of new tires. That is the whole electrical scope. Nothing about auto storage lifts requires exotic wiring, but you want to rough it in early. Our related writeup covers lift electrical planning in detail.
Step 5: Plan the tire rotation and wheel work zone
Tire and wheel work is the most common at-home job on a storage lift, and it is different from other service work because you need floor space around the raised vehicle to spin wheels and stage new tires. Plan at least 4 feet of clear floor on both sides of the lift for tire work. If you stack lifts side by side without walk-around space, you will do tire rotations one at a time, which defeats the point. His original floor plan had the lifts too close together. We shifted the layout by 18 inches to give him full walk-around access on both units. That change happened in a five-minute phone call before framing started and cost him nothing.
Step 6: Heat, insulation, and lift longevity
Cold storage garages beat up lift hydraulics. Below freezing, the hydraulic fluid thickens and the raise cycle slows to a crawl. Below 20 degrees, the seals get brittle faster than the manufacturer warranty accounts for. If you can afford insulation and a small propane or electric heater to hold the shop above 45 degrees in winter, do it. Lift life doubles under those conditions. He spec’d R-19 walls, R-38 ceiling, and a wall-mounted electric heater. Total upcharge was manageable, and the finished shop stays livable year-round. This is where auto storage lifts earn their keep: warm garage, cold car, easy access.
Step 7: Order the lifts on the drywall week
Final sequencing tip. Order the lifts when the drywall goes up, not before. Concrete needs 28 days to cure to full anchor strength, so if you pour early in the build and finish drywall around week 10 to 12, the slab is ready and the shop is clean. We schedule delivery for the week after drywall paint dries. Anchor drilling makes concrete dust, so you want it done before you move tools in. He followed this sequence exactly. Slab poured on day one, walls framed by week three, electrical by week five, drywall by week ten, lifts installed by week twelve. Move-in the following weekend. Call 800-674-9302 to start the planning conversation before your slab pours.

Our Clients Include: