Looking for an Automotive Lift for sale? 

Experience America’s Highest and Most Reviewed Car Lift Installation, Repair, Inspection, and Hydraulic Cylinder Service Company Today!

Car Lift Repair Ames Stars

Read Reviews Buy a Lift

Our Clients Include:Social Proof Car Lift Repair Ames Auto Lift Services

Automotive Two Post Lifts: Sequencing a Dubuque Shop Build-Out

Alignment Machine For Sale Boca Raton, FL

Contact Us

A third-generation family garage in Dubuque called us to plan a shop expansion that would double their bay count and finally give them dedicated space for suspension and shock work. The build-out involved pouring a new slab, running new electrical, and adding air lines, and the owner wanted to sequence the whole project so the automotive two post lifts landed at exactly the right point. Get it wrong and the lifts sit in crates while the electrician is still pulling wire; get it right and the crew is doing shock work in the new bay the week after the concrete cures. This is the technical deep-dive we ran with him, with the real dimensions from a Dubuque bay.

Shop 2-Post Lifts →

Automotive two post lifts for shop expansions and new build-outs across eastern Iowa and the Dubuque tri-state area. We coordinate delivery around your concrete cure, electrical rough-in, and air line install so the lift lands when the bay is ready.

Sequencing a Dubuque shop expansion around lifts

The Dubuque shop had run four bays for two decades, all with older single-post rotary-style machines that had outlived their useful service life. The expansion added two new bays on the east side of the building, and the owner wanted modern two-posts in all six bays after the project settled. That meant the two new bays would open with new automotive two post lifts, and the four existing bays would get their old machines replaced over the following twelve months as the shop budget allowed. Sequencing the initial two-bay install was the piece we spent the most time on.

The sequence we landed on ran in this order: concrete pour on day one, cure through day 28, electrical rough-in during weeks two and three with conduit stubbed for the future air lines, lift delivery scheduled for day 30, install days 31 and 32, air line install days 33 through 35, and full production start on day 40. That timeline built in a week of buffer at the back end for punch-list items, and it kept the lifts from arriving before the slab could safely hold anchors. Every step had a specific dependency, and the biggest risk was the concrete cure running long if the pour weather was cold. We built the schedule with weather buffer.

Concrete, then lifts, then air lines: why the order matters

Concrete has to cure fully before you drill anchors into it, and every manufacturer of automotive two post lifts specifies a minimum 28-day cure at temperatures above 50 degrees Fahrenheit before anchor install. Cure time is not just about the concrete being dry to the touch; it is about the internal chemistry reaching the design strength that the anchor’s holding capacity is rated against. Anchoring into green concrete is a genuine safety risk, and no reputable installer will do it. If your pour happens in cold weather, cure time extends and you need to know that going in.

Lifts have to be installed before air lines run overhead in most shops, because the air line routing needs to avoid the lift’s raised column position and the overhead beam if the machines are overhead configuration. Running air lines first and then discovering that a line crosses the shutoff bar path means moving the air line, which costs more than sequencing it right the first time. On the Dubuque shop, we walked the ceiling with the owner and marked exact locations for air drop points and reel mounts before the electrician finished the electrical rough-in, so the electrician could avoid those spots with conduit runs.

Suspension work: arm reach and pad position

Suspension and shock replacement is one of the workflows where two-post arm reach genuinely matters. Front strut work on a modern passenger vehicle wants the tires hanging free with the vehicle raised at the frame or subframe pickup point, and the arms need to swing far enough to catch those points cleanly. On automotive two post lifts with standard-length asymmetric arms, most passenger vehicles and half-ton pickups reach fine. On extended-frame trucks and full-size SUVs, the rear arms sometimes need to swing further back than the standard configuration provides.

Both Rotary and Challenger offer long-arm packages for shops that regularly work on long-wheelbase vehicles, and we specified the long-arm option on both of the Dubuque shop’s new machines because their mix skews toward crew-cab pickups and extended vans. The additional cost is modest and the reach flexibility is meaningful over a five-year ownership window. Pad height selection also matters: for shock towers with tight frame clearance, having a pad set that includes both low-profile and stack adapters covers essentially every job. We include a full pad set on every install we quote. Our pad adapter guide covers the specific stackups.

Ceiling clearance for shock towers

Shock replacement wants the vehicle high enough that the tech can work under the wheel well with tools swinging freely, which means the vehicle typically sits at least five and a half feet off the ground for a passenger car and closer to six and a half feet for a truck. Add the vehicle height on top of that and you can be looking at eleven or twelve feet from the floor to the top of the raised vehicle for a tall truck. The shop’s ceiling has to accommodate that plus the shutoff bar clearance on overhead automotive two post lifts.

The Dubuque shop’s new bays were poured with a 14-foot ceiling specifically to give the shock and suspension workflow room to breathe. That is generous by home-shop standards and comfortable by commercial-shop standards. A 12-foot ceiling would have worked for the passenger car mix but would have felt tight on the truck side. Ceilings between 11 and 12 feet are workable but require careful lift model selection to make sure the shutoff bar is not immediately at the deck of every raised full-size vehicle. If you are pouring new concrete for a shop expansion, we recommend planning for 14 feet if the budget and roofline allow it.

Air line routing overhead

The air line routing on the Dubuque install was one of the sequencing details that saved the project time. We planned four overhead drops, two per bay, with a reel at each front column and a fixed drop at each rear position. The overhead beams of the two automotive two post lifts sit at exactly the height the air lines needed to run, so we mapped a route that ran the copper lines up and over the lift beam supports and back down at the drop points, staying above the shutoff bar path in all cases. The plumber ran the lines during the two days after the lift install.

The lesson from this piece of the sequence was that the air line contractor needed to see the installed lift before running his lines, not the drawings. Drawings show the nominal beam height and the nominal column position, but the actual installed position varies by a small amount based on anchor placement and slab flatness. Running his copper based on drawings would have put one line six inches too close to the shutoff bar on the raised position, which would have failed inspection. Seeing the installed machine first meant the copper landed clean and the shop passed inspection on the first walkthrough.

Lighting placement for shock work

Shock work at the top of a strut tower wants a specific kind of light: bright, aimed under the raised vehicle, and positioned so the tech’s head does not cast a shadow on the work. The Dubuque shop installed high-CRI LED shop lights on tracks that ran perpendicular to the lift’s fore-aft axis, which meant the tech could slide a light directly over the wheel well from either side. That placement made a real difference in the first month of production; earlier bays in the shop had lighting mounted in the ceiling grid, which threw good general light but poor task light on strut work.

For anyone planning lighting around new automotive two post lifts, the guidance we give is simple: put your best task lighting on tracks or arms that can move to the vehicle, not fixed in the ceiling. General ambient lighting from the ceiling covers walking around and general shop function; targeted task lighting from movable fixtures covers the actual work at the wheel and underhood. Both matter, but only one of them makes shock work faster. The Dubuque owner told us six months in that the lighting decision paid for itself in the first month on strut work alone.

Six-month review of the build-out sequence

At the six-month mark, we walked the shop with the owner to review what the sequence delivered and what we would change. The two new bays came online exactly when planned, and production on the automotive two post lifts hit steady-state within two weeks of the first job. The concrete cure ran three days longer than the ideal 28 because a cold snap pushed the internal temperature down; we had built four days of buffer, so it did not affect the schedule. The electrical rough-in and air line install both finished on time.

The thing we would change is the punch-list buffer at the end. We had planned five days and used four, but if the roof inspection had failed and required a revisit, the buffer would have been too tight. On future shop build-outs of this size we now recommend seven to ten days of buffer between the last major trade and full production start. For anyone in the tri-state area planning a similar expansion, call 800-674-9302 and we will walk your project timeline with you. Good sequencing is the difference between an expansion that hits on schedule and one that drags into month three of missed revenue.

About the Author

Josiah Ragsdale is the founder of Auto Lift Services. Based in Ames, Iowa, our team installs, services, and stocks parts for every major lift brand — from a home-garage 4-post through 30,000 lb commercial and 40K+ heavy-duty. Have a question or need a quote? Call 800-674-9302 or email founder@autoliftserv.com.

Get in Touch

Schedule Your $1 First Service Call!