A quick-lube franchise operator in Ames called us mid-remodel, oil change bays half torn up, asking how a Forward I10 fits into a build-out that was already underway rather than planned from the ground up. That’s a more common situation than starting from a blank slab, and it changes the cost breakdown significantly. A Forward I10 in-ground lift is a strong fit for high-volume oil change and fluid service work because it gives techs full underside access without a post or arm in the way, but the sequencing of when the lift goes in relative to plumbing, drains, and flooring can add or save real money. Here’s how we break the cost down and sequence the build-out correctly.

Shop In-Ground Lifts →

See Forward in-ground packages built for high-volume oil change bays, then talk to us about sequencing your build-out around plumbing and drains.

Why Quick-Lube Operators Choose a Forward I10 Over Surface-Mount Lifts

Most quick-lube bays we work with in Ames run two-post surface-mount lifts, and those work fine for the job. But a growing number of multi-bay operators are asking about a Forward I10 specifically because of throughput. With no posts or arms cluttering the bay, techs can work oil change and fluid service on multiple sides of the vehicle at once without maneuvering around lift columns, and there’s no swing-arm setup time between vehicles. For a franchise pushing volume during peak hours, shaving even a minute or two per car off setup time adds up fast across a full day of oil changes.

The tradeoff is cost and disruption. A Forward I10 costs more upfront than a comparable surface-mount two-post lift once you factor in the pit excavation and concrete work, and it can’t be installed as an afterthought bolted to an existing slab — it requires a real construction phase. For a franchise operator planning a new build or a full gut renovation, that tradeoff often makes sense because the pit goes in while the floor is already open. For a franchise trying to add a Forward I10 to a bay that’s fully finished and operating, the cost calculus shifts, and we walk that through honestly before anyone signs off on it.

The Cost Breakdown: Lift, Concrete, and Everything Between

Breaking down a Forward I10 project into its real cost components helps operators budget accurately instead of getting surprised mid-project. The lift itself — cylinders, footpads, power unit, controls — is one line item, and it’s often not the biggest one once excavation and concrete enter the picture. Pit excavation, forming, rebar, and the structural concrete pour typically represent a substantial share of total project cost, more in older buildings where the existing slab has to be cut out and disposed of before new pit walls can go in.

Beyond the pit itself, plumbing and drain relocation is a line item that catches a lot of operators off guard. If oil change drains, floor drains, or fluid recovery lines run through where the pit needs to go, those get rerouted, which means additional trenching and possibly permit coordination with the city of Ames. Electrical for the power unit, sometimes a new sump pump for pit drainage, and finish flooring around the new pit opening round out the breakdown. We give every quick-lube operator a line-item quote rather than a single number, because seeing where the money goes makes it easier to decide where to spend and where to hold the line.

Garage Build-Out Sequencing: What Goes First

Sequencing is where a lot of build-outs go sideways, and it’s exactly what this operator called us about. The order matters: demolition and excavation come first, then any plumbing or electrical rerouting that needs to happen underground or under-slab, then the pit forming and rebar, then the concrete pour, then the cure period, then the lift installation itself, and finally finish work like flooring and striping around the bay. Trying to install the Forward I10 before plumbing rerouting is finalized is one of the most common sequencing mistakes we see, because it often means breaking out fresh concrete to run a line that should have gone in during the open-excavation phase.

For a franchise operator working on a live remodel with existing bays still trying to serve customers, sequencing also has to account for keeping at least some bays operational. We plan phased build-outs where one or two bays close for the Forward I10 pit work while others keep running oil changes, then rotate. That keeps revenue coming in during a project that otherwise could take several weeks from demo to a lift being load-ready, and it’s a conversation we have early rather than after the concrete crew shows up and the whole shop realizes every bay is closed at once.

Cure Time and Why It Can’t Be Compressed for a Fast-Moving Franchise

Franchise operators run on tight timelines, and it’s fair to want a Forward I10 bay back in service as fast as possible. But concrete cure time is physics, not scheduling preference. A structural pour around an in-ground pit needs several weeks of cure before it’s ready to bear the load of vehicles and the lift itself, regardless of how much pressure there is to reopen the bay. We’ve had operators ask if a faster-curing concrete mix could shrink that window, and while accelerated mixes exist, we don’t recommend cutting corners on a structural pour that a lift and vehicles will sit on for the next twenty years to save a week or two now.

What we can control is everything around the cure window. While concrete cures, we schedule electrical hookup, order and stage the lift components, and get inspections lined up so that the day the pit is ready to load, installation starts immediately rather than waiting on parts or permits. That kind of parallel scheduling is how we keep an Ames build-out on a realistic timeline without pretending the concrete will cure faster than it actually does.

Ongoing Costs After the Forward I10 Is Installed

The cost breakdown doesn’t end at installation. In-ground lifts have different maintenance profiles than surface-mount equipment, and a quick-lube operator running a Forward I10 at high volume needs to budget for it. Hydraulic fluid changes, cylinder seal inspections, and periodic pit drainage checks are part of routine upkeep, and because the cylinder sits below grade, water intrusion is a bigger long-term risk than it is for a two-post lift sitting entirely above the floor. We recommend a maintenance schedule from day one, not after the first issue shows up, since catching a slow leak early is far cheaper than replacing a cylinder that’s corroded from sitting in standing water.

Annual inspection costs, occasional seal kits, and the eventual cylinder service further down the road should all be part of how a franchise operator thinks about total cost of ownership for a the lift, not just the sticker price of the lift and the concrete work to install it. We build these numbers into the same quote conversation we have about the initial build-out, so there are no surprises three or five years down the line when the first service call comes in.

What Ames Franchise Operators Should Ask Before Signing Off

Before committing to a the lift for a quick-lube build-out, we tell every operator to ask a short list of questions. How many bays will be down and for how long during the pit work? What’s the full line-item breakdown, not just a lump sum? Who’s coordinating plumbing and electrical rerouting, and is that included in the quote or a separate contractor? What’s the realistic cure time given the season, since Ames winters slow concrete cure the same way they do everywhere else in Iowa?

Getting straight answers to those questions before the first jackhammer starts is what separates a build-out that finishes on budget from one that drags on with change orders. We walk every Ames-area operator through this same list because a the lift project touches concrete, plumbing, electrical, and equipment all at once, and the operators who plan for that complexity upfront are the ones who reopen bays on schedule and under the number they expected going in.

About the Author

Josiah Ragsdale is the founder of Auto Lift Services. Based in Ames, Iowa, our team installs, services, and stocks parts for every major lift brand — from a home-garage 4-post through 30,000 lb commercial and 40K+ heavy-duty. Have a question or need a quote? Call 800-674-9302 or email [email protected].